Jakarta (ANTARA News) - Toll road developer and operator PT Jasa Marga said it is optimistic the construction of the Pandaan-Malang toll road project would be completed as scheduled on synergy between stakeholders.

By early September, construction of the Pandaan-Malang toll road project was already 66.24 percent completed and land clearing has been 90 percent finished, Chief Executive of the state-owned company Agus Purnomo said here on Monday.

JPM, a subsidiary of Jasa Marga is the operator of the toll road.

The Pandaan-Malang toll road project is divided into five sections. The Sectio I Pandaan-Purwodadi is 15.47 km. Section II Purwodadi-Lawang 8.05 km, Section III Lawang-Singosari 7.10 km, Section IV Singosari-Pakis 4.75 km and Section V5 Pakis-Malang 3.11 km.

The concession of Pandaan-Malang toll road project is for 35 year to cost around Rp5.9 trillion. The Pandaan-Malang toll road would be connected with the Gempol-Pandaan toll road.

Reporting by Edy Sujatmiko